GOES-19 Post-Launch Testing and Transition to Operations
GOES-U launched on June 25, 2024, and was renamed GOES-19 upon reaching geostationary orbit on July 7, 2024.
GOES-19 arrived at its checkout location of 89.5 degrees west longitude on July 18, 2024, and began post-launch testing (PLT) on July 24. The test campaign will ensure that spacecraft subsystems and instrument payloads are calibrated to meet mission performance requirements.
PLT will last approximately six months. NASA will then hand GOES-19 over to NOAA, which will continue checking out the satellite’s data products. NOAA plans to begin drifting GOES-19 from its checkout location to its operational location of 75.2 degrees west longitude in March 2025. GOES-19 is planned to take over as NOAA’s operational GOES-East satellite in April 2025. GOES-16, the current operational GOES-East, will become the on-orbit standby.
GOES-East Transition Plan for Operationalization of GOES-19
Details as of June 17, 2024
Please Note: The following dates are subject to change based on launch, on-orbit checkout activities, and operational needs.
COLOR KEY: | GOES-East Operational Satellite |
Tables scroll horizontally on smaller windows and devices.
Date (Based on 6/25/24 Launch) | GOES-16 | GOES-19 | ||
---|---|---|---|---|
Date | Location | Activity | Location | Activity |
6/25/24 – 7/24/24 | 75.2°W | GOES-East Operations | Launch and Orbit Raising | |
7/25/24 – 1/25/25 | 89.5°W | GOES-19 PLT and PLPT
|
||
1/28/25 | GOES-19 Handover Readiness Review (HRR) | |||
1/29/25 | GOES-19 Handover to NOAA | |||
1/29/25 – 3/17/25 | GOES-19 Pre-Drift Product Checkout
|
|||
3/17/25 – 4/1/25 | GOES-16 “nudge“ to 75.5°W | GOES-19 Drift from 89.5°W to 75.2°W
|
||
4/1/25 | 75.5°W | GOES-16 in co-location configuration
|
75.2°W |
GOES-19 arrives at 75.2°W and instruments resume
|
4/1/25 – 4/4/25 |
GOES-16 in co-location configuration
|
GOES-19 Post-Drift Product Checkout at new location
|
||
4/3/25 | GOES-19 Operational Transition Readiness Review (OTRR) | |||
4/4/25 |
X-band downlink off and instruments shut down
|
GOES-19 Declared operational GOES-East
|
||
4/4/25 |
Begin GOES-16 drift to 105°W
|
|||
6/4/25 | 105°W |
GOES-16 arrival at 105°W followed by storage mode
|